Summary

A crew member received an electrical shock while stripping insulation during replacement motor work. The isolation omitted a space-heater supply in the test position, and a generic motor drawing had been used. The flash stresses equipment-specific drawings in permit-to-work and lockout/tagout procedures when determining isolation.

Topics

About This Record
Publisher
International Marine Contractors Association
Type
Safety Flash
Reference
IMCA SF 14/15
Date
2 October 2015
Topic
Electric Shock, Electrical Safety
Activity
Electrical Isolation, Electrical Work
Control
Energy and Process Isolation, Lockout and Tagout, Permit to Work
Link
Checked , working
Record
imca-sf-14-15-electrical-shock-failure-of-isolations-and-barriers · added 1 September 2026

Report a problem with this record