Summary

This safety flash summarises JFD’s investigation of lacquer blistering and excessive aluminium-neck corrosion in COBRA’s 2L composite cylinders. It distinguishes manufacturer assurances about lacquer defects from unresolved batch concerns, and advises external-condition checks whenever sets leave the dive system, with replacement and IDEST inspection before re-use where condition is questionable.

Topics

About This Record
Publisher
International Marine Contractors Association
Type
Safety Flash
Reference
IMCA SF 21/21
Date
30 July 2021
Topic
Corrosion, Pressure Systems
Activity
Diving Operations, Inspection and Maintenance
Equipment
Gas Cylinder
Control
Pre-Use Checks
Link
Checked , working
Record
imca-sf-21-21-cobra-bailout-system-guidance-note · added 1 September 2026

Report a problem with this record