Summary

A near miss involved unintended deployment of pipeline end termination outriggers after a rigger cut a restraining ratchet strap rather than a rope lanyard. The flash examines absent mechanical locking, changed rigging arrangements, overlooked stored energy and informal communication, with lessons on design risk review and robust management of change.

Topics

About This Record
Publisher
International Marine Contractors Association
Type
Safety Flash
Reference
IMCA SF 25/18
Date
9 November 2018
Topic
Line of Fire, Risk Management
Activity
Rigging
Equipment
Lifting Accessories, Wire Rope
Control
Management of Change, Risk Assessment, Safety Communication