Investigation Report

Hydrocarbon Release During Return to Production After Well Work

BSEEBureau of Safety and Environmental Enforcement

02-01-2013 16:10 00680 WC 20 Shutdown from Gas Release

Read at BSEEOpens the document on bsee.gov

Summary

Investigation of a hydrocarbon release at West Cameron 20-D during return to production after well work. A closed receiving-platform valve left no flow path, overpressurising the departing pipeline and causing gasket failure. Findings identify missing safety-system tests, pre-startup review, regulatory notification and coordination of valve alignment.

Topics

About This Record
Original title
02-01-2013 16:10 00680 WC 20 Shutdown from Gas Release
Publisher
Bureau of Safety and Environmental Enforcement
Type
Investigation Report
Date
Unknown
Topic
Hydrocarbon Release, Mechanical Failure, Pressure Systems
Equipment
Process Pipework and Pipelines, Valve
Control
Functional Testing, Operating and Work Procedures, Safety Communication
Sector
Upstream Oil and Gas
Setting
Offshore Installation
Link
Checked , working