Summary

Guidance for offshore duty holders on assuring temporary refuge HVAC fire-damper performance and maintaining protective pressurisation. It examines full-loop testing, closure indication and timing, detector arrangements, pressure-decay measurement and leakage inspection. Inspection findings inform recommendations on test frequency, access and maintenance records, with reference to relevant offshore regulations.

Topics

About This Record
Publisher
UK Health and Safety Executive
Type
Guidance
Reference
Offshore Information Sheet 1/2006
Date
2006
Topic
Barrier Management, Fire, Regulation and Legislation, Structural and Asset Integrity
Activity
Inspection and Maintenance, Pressure Testing
Equipment
Gas Detector
Control
Fire Protection, Functional Testing, Risk Assessment, Ventilation
Sector
Upstream Oil and Gas
Setting
Offshore Installation