Safety Flash

Lifting post failure on survey equipment

IMCAInternational Marine Contractors AssociationIMCA SF 03/12

Lifting post failure on survey equipment

Read at IMCAOpens the publisher’s page on imca-int.com

Summary

A survey equipment lifting post fractured during deployment through the splash zone at about 5 m depth. A safety tether and electrical umbilical retained the equipment, which divers re-rigged for recovery. The investigation identified inadequate allowance for splash-zone forces; actions included suspending the arrangement and requiring a basket with certified lifting points pending suitable design and testing.

Topics

About This Record
Publisher
International Marine Contractors Association
Type
Safety Flash
Reference
IMCA SF 03/12
Date
4 April 2012
Topic
Mechanical Failure, Structural and Asset Integrity
Activity
Diving Operations, Lifting Operations, Rigging
Equipment
Lifting Accessories
Control
Positive Retention and Reliable Securing, Stop-Work Authority
Setting
Subsea
Link
Checked , working