During tandem bunkering at sea, a mooring rope parted under intermittent jerking as both vessels yawed. Fuel transfer had not begun because the receiving vessel’s pump would not start. The empty hose subsequently parted during tugger-winch retrieval after becoming entangled. The flash discusses postponing operations pending pump readiness or improved weather.

Topics

About This Record
Publisher
International Marine Contractors Association
Type
Safety Flash
Reference
IMCA SF 18/17
Date
25 July 2017
Topic
Mechanical Failure
Activity
Bunkering, Mooring Operations
Equipment
Hose, Mooring Lines, Pumps
Control
Stop-Work Authority
Sector
Marine Industry
Setting
Vessel
Link
Checked , working
Record
imca-sf-18-17-parting-of-hawser-and-bulk-cargo-hose-during-tandem-mooring · added 1 September 2026

Report a problem with this record